Construction of the sewage river was covered with soil half. Zhu Jia Leishe
reporter (Reporter Wang Weiwei Zhang Chunxiao trainee journalist) about 8 am yesterday,
vibram kso, nearly a hundred owners of West Park, Changping Xing Qing Road, No. 8 North to the Beijing office door Sany before the trucks, clean trucks will block many doors nearly 10 hours to protest against the municipal sewage pipeline business transformation. Previously, due to blocked sewage pipes, Xing Park, 26 residents of the home was filthy black mud and manure and other materials are flooded. Yesterday, Changping District Water Authority confirmed, Sany Heavy Industry is secretly laying sewage pipes.
>> incident
26 户 Pan basement sewage
8 o'clock yesterday morning,
five fingers discount,
男子用乙醚将女子迷昏拍裸照, nearly a hundred owners gathered in front of Sany Heavy Industry Beijing Branch . 11:00, Sany Heavy Industry Beijing branch of the factory gate were got from the truck owners, clean vehicles, and other block, the owners are sitting at the door in twos and threes.
31 evening, Changping dump heavy rain, the rain started not long pan basement sewage, fecal matter and other contamination also will be on the Bay. Liu Ping, immediately to the village and 110 called. The district's project manager and the village head Mr. Yan Ma rushed to the scene after another. The inventory, 1,2-night Xing Park West, Building 26 dwelling in the basement flooded.
>> Search for
area blocked sewage pipes
Mr. Ma said,
Vibram 5 Fingers, the building has been completed more than 4 years previously did not show similar problem. At 7:00 on June 1, he took about 30 maintenance team investigate the cause of two routes.
Ma said, when he drove the southwest side of the factory inspections to Sany Heavy Industry, and found someone in the sewage ditch next to the construction of the original six or seven meters wide channel has been left less than 1 meter, the main road near residential sewage, and now such a small displacement definitely not enough.
day, the town is responsible for flood control Huilongguan work Zhangzhen Chang arrived at the scene, asked Sany
>> response
enterprise known as the transformation of the environment
Deputy General Manager Mr. Han said, because of drainage ditch near the business, many of the upstream area, villages and small factories, and no sewage treatment station, all sewage and wastewater plants are directly discharged into the ditch, strong odor.
modified without the Water Authority for approval
construction and management, Changping District Water Authority Chief Mr. Duan said,
vibram fivefingers, this has not yet control the sewage ditch,
Man cheated by false 60 million land-sublease agre,
Vibram Five Fingers, a the ongoing management of town government. According to regulations, Sany Heavy Industry Construction in this river should be reported to the Changping District Water Authority and the town government, but after investigation, Sany Heavy Industry not reported, is secretly laying sewage pipes.
this, the town is responsible for flood control Huilongguan work Zhangzhen Zhang said it was a meeting to resolve the matter, temporarily will do more to explain.
last night around 6, the owners have blocked the main entrance to the clean drive away. >> Survey